[ARCHIVED] Four Corners - Sewer Project

Four Corners Sanitary Sewer Project

Week of August 19th

Baltazar Contractors, Inc. will continue with pipe installation near the intersection of Route 195 and Route 44 during the hours of 8:30am and 4:00pm. There may be alternating traffic with flaggers, expect some delays.

Baltazar Contractors, Inc. will have another crew working in the stream crossings and on Route 44 towards Cedar Swamp Road.

The weather may prevent Baltazar Contractors, Inc. from adhering to this schedule.

If you have any questions, please call our Administrative Office at 860-429-3331.