Baltazar Contractors will be testing the gravity sewers and force mains this week. They are also cleaning up and performing restoration of all areas. The building foundations will be poured at Willard's Pump Station and the walls at Jensen's Pump Station. On Thursday, some work will be done on Route 195 where conduits have to be repaired.